Archive: MS Project and EVM BCWP Calculation

Budget 250$ per month
Posted: 5 years ago
Closed
Description
Hi,
I am looking some guidance on how MS Project calculates BCWP at a task level (as opposed to assignment level). I have a simple schedule for 1 resource working for £10 / hr (8 hr day) on a 5 day task. Total task duration 40 hours at baseline.

At the end of day 1 the resource has worked 7 hours and estimates 30 hours remaining i.e. total estimated hours 37.

I understand how BCWP is calculated at the assignment level (£75.68) but not at the task level (£73.68)

Thanks